1. A factory sets a daily production target of 800 units. At the end of the day, actual production is found to be 650 units. The manager investigates and discovers that 2 machines were non-functional. Which corrective action is MOST appropriate?
- Reduce the production standard to 650 units
- Dismiss the workers for underperformance
- Repair the machines (change inputs) so future production meets the 800-unit standard ✓
- Ignore the deviation as it was caused by equipment, not workers
Correct answer: C — The standard of 800 units is realistic (it was met before the machines broke down). The root cause is equipment failure, so the corrective action is to fix/replace the machines — changing inputs — not to revise the standard or blame workers.
2. A company is developing a new satellite launch vehicle — a highly complex project with many activities whose durations depend on testing outcomes. Which project management technique should they use?
- PERT — because activity durations are uncertain and probabilistic, requiring three time estimates ✓
- CPM — because the critical path needs to be identified
- Budgetary control — because it is a large financial project
- Ratio analysis — to compare project costs with industry benchmarks
Correct answer: A — PERT is designed for novel, complex projects with uncertain durations. Its three time estimates (optimistic, most likely, pessimistic) handle the uncertainty inherent in first-of-kind R&D and defence projects. CPM would apply only if durations were deterministically known.
3. Planning and Controlling are called 'inseparable twins' because:
- Both are performed only by top management
- Both require large financial investment to implement
- Plans provide the standards for controlling; controlling measurements feed back into future plans — each gives meaning and effectiveness to the other ✓
- Both were developed at the same time in management theory
Correct answer: C — Planning and controlling are mutually dependent: without plans, there are no standards to measure against (controlling is blind); without controlling, plans remain mere intentions with no mechanism to ensure achievement. The feedback loop between them makes both functions effective.